Decision No. 14/2000/QD-BXD dated July 20, 2000 of the Ministry of Construction promulgating investment and construction consultancy expense norms
- Summary
- Content
- Status
- Vietnamese
- Related documents
- Diagram
- Download
Please log in to your Advanced Package to view the full text. Do not have an account yet? Register here.
Please log in to use this function
Please log in to use this function
ATTRIBUTE
| Issuing body: | Ministry of Construction | Effective date: |
Known
Please log in to a subscriber account to use this function. Don’t have an account? Register here |
| Official number: | 14/2000/QD-BXD | Signer: | Nguyen Manh Kiem |
| Type: | Decision | Expiry date: |
Known
Please log in to a subscriber account to use this function. Don’t have an account? Register here |
| Issuing date: | 20/07/2000 | Effect status: |
Known
Please log in to a subscriber account to use this function. Don’t have an account? Register here |
| Fields: | Construction |
The Effect status of this document is known.This feature is available to Advanced account holders. Please log in to a subscriber account to view Effect status. Don’t have an account? Register here
|
THE MINISTRY OF CONSTRUCTION
------- |
SOCIALIST REPUBLIC OF VIET NAM
Independence - Freedom - Happiness ---------- |
|
No: 14/2000/QD-BXD
|
Hanoi, July 20, 2000
|
Pursuant to the Government’s Decree No.15/CP of March 4, 1994 defining the functions, tasks, powers and organizational structure of the Construction Ministry.
Pursuant to the Government’s Decree No.52/1999/ND-CP of July 8, 1999 promulgating the Regulation on Investment and Construction Management and Decree No.12/2000/ND-CP of May 5, 2000 amending and supplementing a number of articles of the Regulation on Investment and Construction Management issued together with the Government’s Decree No.52/1999/ND-CP of July 8, 1999.
At the proposal of the director of Construction Economics Institute,
|
|
MINISTER OF CONSTRUCTION
Nguyen Manh Kiem |
(Issued together with the Construction Minister’s Decision No.14/2000/QD-BXD of July 20, 2000)
|
Ck
|
=
|
Cd
|
x
|
TGk (2)
|
|
TGd
|
|
Nit
|
=
|
Nib
|
-
|
﴾
|
(Git - Gib)
|
Nib - Nia
|
)(3)
|
|
Gia - Gib
|
|
Ordinal number
|
Contents of expenses
|
Exposition of expenses
|
In cash (VND)
|
|
1
|
Materials expense:
|
Volume x unit price
|
|
|
|
- Paper
|
|
|
|
|
- Stationery...
|
. . . . .
|
|
|
2
|
Labor-hiring expense:
|
|
|
|
|
- Wages and wage allowances
|
|
|
|
|
+ Chief consultant
|
Work x unit price
|
|
|
|
+ Engineer A...
|
. . . . .
|
|
|
3
|
Machinery and equipment expense:
|
|
|
|
|
- Computers
|
. . . . .
|
|
|
|
- Other machinery (equipment)
|
. . . . .
|
|
|
4
|
General expenses
|
70% x (2)
|
|
|
5
|
Pre-calculated taxable income
|
6% x (1+ 2 + 3 + 4)
|
|
|
6
|
Output VAT
|
VAT rate prescribed for consultancy work x (1+ 2 + 3 + 4 + 5)
|
|
|
|
Total:
|
|
|
|
Project group
|
Job description
|
Construction, installation and equipment value without vat (billion VND)
|
||||||||||
|
I
|
|
< 1
|
1
|
5
|
15
|
25
|
50
|
100
|
200
|
500
|
1,000
|
=2,000
|
|
|
1. Elaboration of pre-feasibility study reports
|
|
|
|
|
|
|
0.068
|
0.053
|
0.044
|
0.031
|
0.019
|
|
|
2. Elaboration of feasibility study reports
|
|
0.790
|
0.719
|
0.575
|
0.489
|
0.388
|
0.288
|
0.244
|
0.201
|
0.173
|
0.144
|
|
|
3. Elaboration of investment reports
|
0.557
|
|
|
|
|
|
|
|
|
|
|
|
II
|
1. Elaboration of pre-feasibility study reports
|
|
|
|
|
|
|
0.045
|
0.035
|
0.029
|
0.020
|
0.012
|
|
|
2. Elaboration of feasibility study reports
|
|
0.396
|
0.360
|
0.264
|
0.240
|
0.192
|
0.156
|
0.121
|
0.096
|
0.084
|
0.072
|
|
|
3. Elaboration of investment reports
|
0.323
|
|
|
|
|
|
|
|
|
|
|
|
III
|
1. Elaboration of pre-feasibility study reports
|
|
|
|
|
|
|
0.046
|
0.036
|
0.030
|
0.021
|
0.013
|
|
|
2. Elaboration of feasibility study reports
|
|
0.454
|
0.413
|
0.303
|
0.275
|
0.220
|
0.179
|
0.139
|
0.110
|
0.096
|
0.083
|
|
|
3. Elaboration of investment reports
|
0.336
|
|
|
|
|
|
|
|
|
|
|
|
IV
|
1. Elaboration of pre-feasibility study reports
|
|
|
|
|
|
|
0.042
|
0.033
|
0.028
|
0.019
|
0.011
|
|
|
2. Elaboration of feasibility study reports
|
|
0.380
|
0.345
|
0.253
|
0.230
|
0.184
|
0.150
|
0.116
|
0.092
|
0.081
|
0.069
|
|
|
3. Elaboration of investment reports
|
0.309
|
|
|
|
|
|
|
|
|
|
|
|
V
|
1. Elaboration of pre-feasibility study reports
|
|
|
|
|
|
|
0.0621
|
0.0483
|
0.0414
|
0.029
|
0.017
|
|
|
2. Elaboration of feasibility study reports
|
|
0.462
|
0.420
|
0.336
|
0.276
|
0.227
|
0.168
|
0.143
|
0.118
|
0.101
|
0.086
|
|
|
3. Elaboration of investment reports
|
0.216
|
|
|
|
|
|
|
|
|
|
|
|
Project group
|
Job description
|
Construction and installation value without vat (billion VND)
|
|||||||||
|
|
|
<= 0.5
|
1
|
5
|
15
|
25
|
50
|
100
|
200
|
500
|
=1,000
|
|
I
|
1. Compilation of construction and installation bidding dossiers and analysis, evaluation of construction and installation bids
|
0.396
|
0.330
|
0.300
|
0.240
|
0.160
|
0.100
|
0.070
|
0.045
|
0.033
|
0.023
|
|
|
2. Supervision of project construction and equipment installation
|
1.782
|
1.485
|
1.430
|
1.342
|
1.188
|
1.008
|
0.787
|
0.616
|
0.500
|
0.330
|
|
II
|
1. Compilation of construction and installation bidding dossiers and analysis, evaluation of construction and installation bids
|
0.277
|
0.231
|
0.210
|
0.168
|
0.115
|
0.080
|
0.050
|
0.030
|
0.023
|
0.016
|
|
|
2. Supervision of project construction and equipment installation
|
1.240
|
1.034
|
0.990
|
0.911
|
0.814
|
0.704
|
0.554
|
0.432
|
0.346
|
0.231
|
|
III
|
1. Compilation of construction and installation bidding dossiers and analysis, evaluation of construction and installation bids
|
0.263
|
0.219
|
0.200
|
0.160
|
0.109
|
0.077
|
0.045
|
0.029
|
0.022
|
0.015
|
|
|
2. Supervision of project construction and equipment installation
|
0.954
|
0.793
|
0.739
|
0.661
|
0.583
|
0.446
|
0.275
|
0.216
|
0.163
|
0.109
|
|
IV
|
1. Compilation of construction and installation bidding dossiers and analysis, evaluation of construction and installation bids
|
0.246
|
0.205
|
0.186
|
0.149
|
0.102
|
0.070
|
0.043
|
0.027
|
0.020
|
0.014
|
|
|
2. Supervision of project construction and equipment
|
0.886
|
0.740
|
0.686
|
0.621
|
0.546
|
0.421
|
0.254
|
0.202
|
0.156
|
0.102
|
|
V
|
1. Compilation of construction and installation bidding dossiers and analysis, evaluation of construction and installation bids
|
0.331
|
0.276
|
0.240
|
0.204
|
0.138
|
0.090
|
0.060
|
0.036
|
0.024
|
0.019
|
|
|
2. Supervision of project construction and equipment installation
|
1.505
|
1.254
|
1.210
|
1.135
|
0.977
|
0.834
|
0.664
|
0.519
|
0.392
|
0.275
|
|
Project group
|
Job description
|
Construction and installation value without vat (billion VND)
|
|||||||||
|
|
|
<= 0.5
|
1
|
5
|
15
|
25
|
50
|
100
|
200
|
500
|
=1,000
|
|
I
|
Compilation of for supplies and equipment procurement bidding dossiers as well as analysis and evaluation of bids therefor
|
0.266
|
0.222
|
0.204
|
0.180
|
0.156
|
0.102
|
0.066
|
0.057
|
0.048
|
0.033
|
|
II
|
Compilation of supplies and equipment procurement bidding dossiers as well as analysis and evaluation of bids therefor
|
0.187
|
0.156
|
0.144
|
0.126
|
0.108
|
0.072
|
0.048
|
0.041
|
0.035
|
0.023
|
|
III
|
Compilation of supplies and equipment procurement bidding dossiers as well as analysis and evaluation of bids therefor
|
0.168
|
0.140
|
0.130
|
0.113
|
0.097
|
0.065
|
0.043
|
0.037
|
0.031
|
0.021
|
|
IV
|
Compilation of supplies and equipment procurement bidding dossiers as well as analysis and evaluation of bids therefor
|
0.157
|
0.131
|
0.121
|
0.106
|
0.091
|
0.061
|
0.040
|
0.035
|
0.029
|
0.020
|
|
V
|
Compilation of supplies and equipment procurement bidding dossiers as well as analysis and evaluation of bids therefor
|
0.223
|
0.186
|
0.168
|
0.156
|
0.132
|
0.084
|
0.054
|
0.048
|
0.041
|
0.028
|
|
Job description
|
Project
group |
Construction, installation and equipment value without vat (billion VND)
|
|||||||||||
|
1. Appraisal of investment projects
|
I- V
|
<= 0.5
|
1
|
5
|
15
|
25
|
50
|
100
|
200
|
500
|
=1,000
|
=2,000
|
|
|
|
|
|
0.0350
|
0.0322
|
0.0266
|
0.0238
|
0.0210
|
0.0175
|
0.0140
|
0.0105
|
0.0067
|
0.0035
|
|
|
|
CONSTRUCTION AND INSTALLATION VALUE WITHOUT VAT (BILLION VND)
|
||||||||||||
|
2. Appraisal of technical designs
|
I
|
0.1436
|
0.1197
|
0.1071
|
0.0945
|
0.0630
|
0.0553
|
0.0441
|
0.0315
|
0.0221
|
0.0158
|
0.0087
|
|
|
|
II
|
0.0983
|
0.0819
|
0.0756
|
0.0630
|
0.0441
|
0.0392
|
0.0309
|
0.0221
|
0.0158
|
0.0113
|
0.0063
|
|
|
|
III; IV
|
0.0932
|
0.0781
|
0.0718
|
0.0599
|
0.0422
|
0.0371
|
0.0296
|
0.0208
|
0.0151
|
0.0107
|
0.0057
|
|
|
|
V
|
0.1344
|
0.1008
|
0.0945
|
0.0819
|
0.0536
|
0.0469
|
0.0378
|
0.0271
|
0.0158
|
0.0139
|
0.0077
|
|
|
3. Appraisal of total cost estimates
|
I
|
0.1260
|
0.1050
|
0.0910
|
0.0700
|
0.0476
|
0.0413
|
0.0315
|
0.0252
|
0.0161
|
0.0133
|
0.0070
|
|
|
|
II
|
0.1512
|
0.1260
|
0.1120
|
0.0840
|
0.0560
|
0.0490
|
0.0371
|
0.0308
|
0.0231
|
0.0161
|
0.0083
|
|
|
|
III; IV
|
0.1057
|
0.0882
|
0.0784
|
0.0588
|
0.0406
|
0.0392
|
0.0259
|
0.0210
|
0.0161
|
0.0112
|
0.0067
|
|
|
|
V
|
0.1008
|
0.0840
|
0.0742
|
0.0560
|
0.0385
|
0.0371
|
0.0245
|
0.0203
|
0.0154
|
0.0105
|
0.0061
|
|
You are not logged in.
This feature is available to Advanced account holders. Please log in to access detailed information on Related documents.
If you do not have an account, please register here!
VIETNAMESE DOCUMENTS
This utility is available to subscribers only. Please log in to a subscriber account to download. Don’t have an account? Register here
ENGLISH DOCUMENTS
This utility is available to subscribers only. Please log in to a subscriber account to download. Don’t have an account? Register here