THE MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT | | THE SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness |
No. 04/2021/TT-BNNPTNT | | Hanoi, June 28, 2021 |
CIRCULAR
Guiding the approval and appraisal of dike-related activities[1]
Pursuant to the Government’s Decree No. 15/2017/ND-CP of February 17, 2017, defining the functions, tasks, powers, and organizational structure of the Ministry of Agriculture and Rural Development;
Pursuant to the November 29, 2006 Law on Dikes; and the June 17, 2020 Law Amending and Supplementing a Number of Articles of the Law on Natural Disaster Prevention and Control and the Law on Dikes;
Pursuant to the November 20, 2018 Law Amending and Supplementing a Number of Planning-related Articles of Thirty-Seven Laws;
Pursuant to the Government’s Decree No. 113/2007/ND-CP of June 28, 2007, detailing and guiding a number of articles of the Law on Dikes;
At the proposal of the General Director of the Vietnam Disaster Management Authority;
The Minister of Agriculture and Rural Development promulgates the Circular guiding the approval and appraisal of dike-related activities.
Article 1. Scope of regulation
This Circular guides the solicitation of the Ministry of Agriculture and Rural Development’s approval of dike-related activities, and appraisal of contents related to flood drainage and dike safety for the Prime Minister-approved construction investment projects implemented on river stretches, sand expanses or islets where exist no construction works.
Article 2. Subjects of application
This Circular applies to agencies, organizations and individuals carrying out dike-related activities.
Article 3. Regulations on approval
1. Activities subject to solicitation of approval from the Ministry of Agriculture and Rural Development include:
a/ Grant of permits for the activities specified at Points a, b, c and h, Clause 1, Article 25 of the Law on Dikes, for dikes of special grade, grade I, grade II, and grade III;
b/ Construction and renovation of dike-related traffic works, for those located in two or more provinces.
2. Contents of consideration and approval
a/ Compliance with the law on dikes;
b/ Conformity with anti-flood master plans for diked rivers, and master plans on dikes; and flood control plans for diked rivers and plans on development of dike systems in provincial-level master plans approved by competent authorities;
c/ Assurance of dike safety and flood drainage during the construction of works;
d/ Flood control solutions in the process of construction of works and dike safety solutions in the management and use of works;
dd/ Measures to ensure traffic safety on dikes in the process of construction of works;
e/ Other relevant matters (if any).
3. Method of solicitation of approval
A provincial-level People’s Committee shall submit to the Ministry of Agriculture and Rural Development two sets of dossier of request for approval, each of which must comprise:
a/ A request for approval, made by the provincial-level People’s Committee;
b/ Written opinions submitted by the provincial-level Department of Agriculture and Rural Development to the provincial-level People’s Committee;
c/ Technical documents approved by the competent authority, including a commentary report and drawings of the general layout and cross sections, which show contents related to dikes and flood drainage during the construction;
d/ Other documents related to the construction and project implementation (if any);
dd/ Documents of People’s Committees of related provinces, for a construction work located in two or more provinces.
4. Receipt and processing of dossiers of request for approval
a/ The Vietnam Disaster Management Authority under the Ministry of Agriculture and Rural Development shall receive and process dossiers of request for approval.
b/ In the process of considering a dossier, if deeming that the concerned construction work is likely to affect dike safety and flood drainage, the Vietnam Disaster Management Authority shall, on a case-by-case basis, request the provincial-level People’s Committee to provide additional documents for consideration and approval, including an independent consultancy unit’s written verification of the construction work’s impacts on dike safety and flood drainage on the riverbed (decrease in the designed flood flow; increase in the designed flood level; impacts on flows in adjacent, upstream and downstream areas; riverbed stability; and stability of dike body and dike foundation in the area where the work is built); written opinions of related competent agencies; and documents on topographical and geological surveys serving inspection and calculation.
c/ In case the dossier is incomplete or requires the additional documents specified at Point b of this Clause, the Vietnam Disaster Management Authority shall, within three working days after receiving the dossier, request the provincial-level People’s Committee to supplement and complete the dossier.
d/ Within fifteen days after receiving a complete dossier under regulations, the Vietnam Disaster Management Authority shall consider and issue a written approval. In case of disapproval, it shall issue a written reply, clearly stating the reason for disapproval, and send it to the provincial-level People’s Committee.