2 cases where EVN may cover unsuccessful investment expenses with after-tax profits

The provisions are specified in the Government's Decree No. 407/2026/ND-CP dated November 12, 2026, prescribing special mechanisms for operation and financial management applicable to Vietnam Electricity.

2 cases where EVN may cover unsuccessful investment expenses

Under Article 5 of Decree No. 407/2026/ND-CP, the Government specifies the cases where Vietnam Electricity (EVN) may cover expenses incurred from unsuccessful investments in electricity projects and works with after-tax profits.

Specifically, Clause 1, Article 5 of Decree No. 407/2026/ND-CP stipulates that expenses to be covered by after-tax profits are expenses incurred from unsuccessful investments in electricity projects and works of a special nature and involving high risks, which are not deductible when determining taxable income in accordance with the law on corporate income tax.

These expenses include investment preparation expenses and investment expenses already incurred in accordance with law for any of the following electricity projects and works:

  • Electricity projects and works that are no longer eligible for implementation due to adjustments to master plans by competent state agencies.

  • Electricity projects and works that are no longer eligible for implementation due to the promulgation or amendment of policies by competent state agencies, resulting in changes to investment conditions, where such changes are the direct and decisive cause of the projects no longer being eligible for implementation.

Regarding dossiers for determining expenses incurred from unsuccessful investments, Clause 2, Article 5 of Decree No. 407/2026/ND-CP stipulates:

For electricity projects and works that are no longer eligible for implementation due to adjustments to master plans, dossiers must comprise:

  • Documents on adjustments to master plans issued by competent agencies, accompanied by reports assessing the impacts of such adjustments resulting in the projects no longer being eligible for implementation; or decisions on policy changes issued by competent agencies and reports assessing the impacts of such policy changes resulting in the projects no longer being eligible for implementation;

  • Dossiers on acceptance testing, payment and finalization of the volume and value of investment survey work performed in accordance with law;

  • Independent auditors' audit reports on the value of expenses incurred.

For electricity projects and works that are no longer eligible for implementation due to policy changes resulting in changes to investment conditions, dossiers must comprise:

  • Decisions on policy changes issued by competent agencies and reports assessing the impacts of such policy changes resulting in electricity projects and works no longer being eligible for implementation;

  • Dossiers on acceptance testing, payment and finalization of the volume and value of work performed, or finalization/determination of the value of investment expenses incurred;

  • Independent auditors' audit reports on the finalized value.

Notably, under Clause 3, Article 5 of Decree No. 407/2026/ND-CP, based on the independent auditor's unqualified audit report on the finalized value, EVN shall decide on the allocation period not exceeding 5 years from the date the Board of Directors approves the eligibility for finalization.

Under Article 6 of Decree No. 407/2026/ND-CP, this Decree takes effect from December 28, 2026, and applies from the 2026 fiscal year.