Decision No. 482/QD-BCT dated February 06, 2018 granting approval for addition of Bach Khoa A Chau 1 solar power plant project (with capacity of 30 Mwp) to the power development plan of Tay Ninh province during 2011 – 2015 with a vision by 2020

  • Summary
  • Content
  • Status
  • Vietnamese
  • Download
Save

Please log in to use this function

Send link to email

Please log in to use this function

Error message
Font size:

ATTRIBUTE

Decision No. 482/QD-BCT dated February 06, 2018 granting approval for addition of Bach Khoa A Chau 1 solar power plant project (with capacity of 30 Mwp) to the power development plan of Tay Ninh province during 2011 – 2015 with a vision by 2020
Issuing body: Ministry of Industry and TradeEffective date:
Known

Please log in to a subscriber account to use this function.

Don’t have an account? Register here

Official number:482/QD-BCTSigner:Tran Tuan Anh
Type:DecisionExpiry date:Updating
Issuing date:06/02/2018Effect status:
Known

Please log in to a subscriber account to use this function.

Don’t have an account? Register here

Fields:Electricity , Industry
For more details, click here.
Download files here.
LuatVietnam.vn is the SOLE distributor of English translations of Official Gazette published by the Vietnam News Agency
Effect status: Known

THE MINISTRY OF INDUSTRY AND TRADE

Decision No. 482/QD-BCT dated February 06, 2018 granting approval for addition of Bach Khoa A Chau 1 solar power plant project (with capacity of 30 Mwp) to the power development plan of Tay Ninh province during 2011 – 2015 with a vision by 2020

Pursuant to the Law on Electricity dated December 03, 2004; the Law on amendments to the Law on Electricity dated November 20, 2012;

Pursuant to the Government’s Decree No. 137/2013/ND-CP dated October 21, 2013 elaborating some Articles of the Law on Electricity and the Law on amendments to the Law on Electricity;

Pursuant to the Government’s Decree No. 98/2017/ND-CP dated August 18, 2017 defining the functions, tasks, powers and organizational structure of the Ministry of Industry and Trade;

Pursuant to the Circular No. 43/2013/TT-BCT dated December 31, 2013 of the Ministry of Industry and Trade providing for establishment, approval and adjustment of the power development plan;

Pursuant to the Circular No. 16/2017/TT-BCT dated September 12, 2017 of the Ministry of Industry and Trade providing for development of solar power projects and standard power purchase agreement applied to solar power projects;

In consideration of the request of the People’s Committee of Tay Ninh Province made in the Official Dispatch No. 1966/UBND-KTTC dated July 27, 2017 requesting for addition of the following solar power plant projects, Bach Khoa A Chau 1 (with capacity of 30 MWp), Bach Khoa A Chau 2 (with capacity of 30 MWp), Minh Viet 1 (with capacity of 30 MWp), Minh Viet 2 (with capacity of 30 MWp), Tri Viet 1 (with capacity of 30 MWp) and Tri Viet 2 (with capacity of 30 MWp), to the power development plan of Tay Ninh Province during 2011 - 2015 with a vision by 2020; the Official Dispatch No. 2956/UBND-KTTC dated November 02, 2017 of the People’s Committee of Tay Ninh Province giving response to the Official Dispatch No. 239/DL-KH&QH on documents concerning the addition of Bach Khoa A Chau 1, Minh Viet 1, and Tri Viet 1 solar power plant projects into the power development plan of Tay Ninh Province; the Official Dispatch No. 1511/CV-BKAC dated November 15, 2017 of Bach Khoa A Chau Power Company Limited on supplementing documents concerning the power development plan of Tay Ninh Province - Bach Khoa A C solar power plant project, which was jointly established and adjusted by the Power Engineering Consulting Joint Stock Company 1 (PECC1) and Vinteg Joint Stock Company (Vinteg) in November, 2017;

At the request of the Director of Electricity and Renewable Energy Authority,

DECIDES:

Article 1. To amend and supplement the power development plan of Tay Ninh Province during 2011 – 2015 with a vision by 2020 are approved herein. To be specific:

1. Bach Khoa A Chau 1 Solar Power Plant Project is added to the power development plan of Tay Ninh Province. To be specific:

- Capacity: 30 MWp, operating in 2019;

- Location: Suoi Day Town, Tan Chau District, Tay Ninh Province;

- Land area: about 60 ha, in which the land area for long-term use is 36 ha, and the land area for temporary use is 24 ha (which shall be exactly determined when preparing the Project's feasibility study report in accordance with the Circular No. 16/2017/TT-BCT dated September 12, 2017 by the Ministry of Industry and Trade providing for development of solar power projects and model power purchase agreement applied to solar power projects).

2. Connection plan:

- Build a new 22/110 kV step-up substation (Bach Khoa A Chau 1 solar power) with a capacity of 40 MVA, operating in 2019 in harmony with the progress of Bach Khoa A Chau 1 solar power plant.

- Build a new 110 kV Recloser (Tay Ninh 1 solar power) on the 110 kV power line from Bourbon to Tay Ninh 220 kV substation, operating in 2019 in harmony with the progress of Bach Khoa A Chau 1 solar power plant (which is used for connection with Tri Viet 1 solar power plant project).

- Build a new 110 kV power line using ACSR120 conducting-wire, with a length of 6 km from the 22/110 kV step-up substation (Back Khoa A Chau 1 solar power) to the 110 kV Recloser (Tay Ninh 1 solar power) (suspended by the same pole used for the 110 kV power line of Tri Viet 1 solar power plant project).

3. The list of other power structures is stipulated in the Decision No. 5905/QD-BCT dated November 11, 2011 of the Minister of Industry and Trade granting approval for the power development plan of Tay Ninh Province during 2011 – 2015 with a vision by 2020 and relevant decisions on amendments and supplements to this power development plan of Tay Ninh Province.

Article 2. Implementation organization

1. The People’s Committee of Tay Ninh Province shall carry out procedures for changes in land-use purposes in accordance with applicable law regulations; allocate land area for executing solar power projects and building substations and power lines in a uniform manner and in conformity with the provincial land-use plan 2016 – 2020.

2. Investors of solar power plant projects shall cooperate with the People’s Committee of Tay Ninh Province, the Vietnam Electricity, and the Southern Power Corporation in raising capital and making investments in work items supplemented to the solar power development plan in accordance with applicable regulations so as to ensure the plan's progress and power supply safety.

3. The investor shall assume responsibility for the investment efficiency of the in-charge project and strictly comply with the Prime Minister’s Feed in Tariff policy.

4. The Department of Industry and Trade of Tay Ninh Province shall supervise, inspect and submit reports on the execution of approved power work items.

Article 3. Implementation effect and responsibility

1. This Decision takes effect on the signing date.

2. Chief of the Ministry Office, Director of Electricity and Renewable Energy Authority, President of the People’s Committee of Tay Ninh Province, Director of Department of Industry and Trade of Tay Ninh Province, General Director of Vietnam Electricity, General Director of Southern Power Corporation and relevant units shall implement this Decision./.

The Minister
Tran Tuan Anh

Please log in to a subscriber account to see the full text. Don’t have an account? Register here
Please log in to a subscriber account to see the full text. Don’t have an account? Register here
Processing, please wait...
LuatVietnam.vn is the SOLE distributor of English translations of Official Gazette published by the Vietnam News Agency

ENGLISH DOCUMENTS

Others
Decision 482/QĐ-BCT DOC (Word)

This utility is available to subscribers only. Please log in to a subscriber account to download. Don’t have an account? Register here

* Note: To view documents downloaded from LuatVietnam.vn, please install DOC, DOCX and PDF file readers
For further support, please call 19006192

SAME CATEGORY

loading