Circular No. 16/2022/TT-BKHDT dated July 29, 2022 of the Ministry of Planning and Investment on ceasing the effect of the Minister of Planning and Investment’s Circular No. 08/2022/TT-BKHDT dated May 31, 2022, stipulating in detail the provision and posting of information on bidding, and selection of contractors via the national e-public procurement system and the Minister of Planning and Investment’s Circular No. 10/2022/TT-BKHDT dated June 15, 2022, providing in detail the provision and publication of information and selection of investors on the Vietnam national e-procurement system
Issuing body: Ministry of Planning and InvestmentEffective date:
Known

Please log in to a subscriber account to use this function.

Don’t have an account? Register here

Official number:16/2022/TT-BKHDTSigner:Nguyen Chi Dung
Type:CircularExpiry date:Updating
Issuing date:29/07/2022Effect status:
Known

Please log in to a subscriber account to use this function.

Don’t have an account? Register here

Fields:Bidding - Competition , Investment

SUMMARY

Cease the effect of Circulars 08/2022/TT-BKHDT and 10/2022/TT-BKHDT relating to bidding

On July 29, 2022, the Ministry of Planning and Investment issues Circular No. 16/2022/TT-BKHDT on ceasing the effect of the Minister of Planning and Investment’s Circular No. 08/2022/TT-BKHDT dated May 31, 2022, stipulating in detail the provision and posting of information on bidding, and selection of contractors via the national e-public procurement system and the Minister of Planning and Investment’s Circular No. 10/2022/TT-BKHDT dated June 15, 2022, providing in detail the provision and publication of information and selection of investors on the Vietnam national e-procurement system.

Accordingly, to cease the effect of Circular No. 08/2022/TT-BKHDT from August 01, 2022, to September 15, 2022, except for the provisions on the roadmap for application of e-procurement for bidding packages for procurement of goods divided into several parts specified in Clause 1, Article 37. To cease the effect of Circular No. 10/2022/TT-BKHDT from August 01, 2022, to September 15, 2022.

During the cessation of effect of Circular No. 08/2022/TT-BKHDT and Circular No. 10/2022/TT-BKHDT:

- For the bidding package for which the bidding dossier has been issued before January 01, 2023, the selection of contractors shall be carried out according to the issued bidding dossier and the provisions of law in effect at that time;

- From January 01, 2023, if the approved bidding package does not apply the online contractor selection and has not yet issued the bidding dossier, the contractor selection shall be organized online on the basis of ensuring of the roadmap specified in Article 37 of Circular No. 08/2022/TT-BKHDT. In such cases, competent persons may not change the contractor selection plan.

This Circular takes effect from August 01, 2022.

For more details, click here.
Download files here.
LuatVietnam.vn is the SOLE distributor of English translations of Official Gazette published by the Vietnam News Agency
Effect status: Known

THE MINISTRY OF PLANNING AND INVESTMENT

­___________________

No. 16/2022/TT-BKHDT

THE SOCIAL REPUBLIC OF VIETNAM

Independence - Freedom - Happiness

____________

Hanoi, July 29, 2022


CIRCULAR

On ceasing the effect of the Minister of Planning and Investment’s Circular No. 08/2022/TT-BKHDT dated May 31, 2022, stipulating in detail the provision and posting of information on bidding, and selection of contractors via the national e-public procurement system and the Minister of Planning and Investment’s Circular No. 10/2022/TT-BKHDT dated June 15, 2022, providing in detail the provision and publication of information and selection of investors on the Vietnam national e-procurement system

______________________________

 

Pursuant to the Law on Bidding dated November 26, 2013;

Pursuant to the Law on Investment in the Form of Public-Private Partnership dated June 18, 2020;

Pursuant to the Law on E-transactions dated November 29, 2005;

Pursuant to the Law on Promulgation of Legal Documents dated June 22, 2015;

Pursuant to the Law Amending and Supplementing a Number of Articles of the Law on Promulgation of Legal Documents dated June 18, 2020;

Pursuant to the Government’s Decree No. 63/2014/ND-CP dated June 26, 2014, detailing a number of articles of the Bidding Law regarding contractor selection;

Pursuant to the Government’s Decree No. 25/2020/ND-CP dated February 28,2020, detailing a number of articles of the Bidding Law regarding investor selection;

Pursuant to the Government’s Decree No. 35/2021/ND-CP dated March 29, 2021, detailing and guiding the implementation of the Law on Investment in the Form of Public-Private Partnership;

Pursuant to the Government’s Decree No. 86/2017/ND-CP dated July 25, 2017, on defining the functions, tasks, powers and organizational structure of the Ministry of Planning and Investment;

At the request of the Director of the Public Procurement Agency;

The Minister of Planning and Investment promulgates the Circular on ceasing the effect of the Minister of Planning and Investment’s Circular No. 08/2022/TT-BKHDT dated May 31, 2022, stipulating in detail the provision and posting of information on bidding, and selection of contractors via the National E-Public Procurement system and the Minister of Planning and Investment’s Circular No. 10/2022/TT-BKHDT dated June 15, 2022, providing in detail the provision and publication of information and selection of investors on the Vietnam National E-Procurement System.

Article 1. Ceasing the effect

The Minister of Planning and Investment’s Circular No. 08/2022/TT-BKHDT dated May 31, 2022, stipulating in detail the provision and posting of information on bidding, and selection of contractors via the National E-Public Procurement system, such Circular shall be:

a) Ceased the effect from August 01, 2022, to September 15, 2022, except for the provisions on the roadmap for application of e-procurement for bidding packages for procurement of goods divided into several parts specified in Clause 1, Article 37.

b) Ceased the effect of the provisions on the roadmap for application of e-procurement for bidding packages for procurement of goods divided into several parts specified in Clause 1, Article 37 from August 01, 2022, to January 01, 2023.

2. To ceased the effect of the Minister of Planning and Investment’s Circular No. 10/2022/TT-BKHDT dated June 15, 2022, providing in detail the provision and publication of information and selection of investors on the Vietnam National E-Procurement System, from August 01, 2022, to September 15, 2022.

Article 2. Transitional provisions

1. During the cessation of effect of Circular No. 08/2022/TT-BKHDT and Circular No. 10/2022/TT-BKHDT, the following legal documents and provisions shall remain effective:

a) The Minister of Planning and Investment's Circular No. 01/2015/TT-BKHDT dated February 14, 2015, detailing the making of dossiers of invitation for expression of interest, bidding dossiers and dossiers of request for consulting services.

b) The Minister of Planning and Investment's Circular No. 03/2015/TT-BKHDT dated May 06, 2015, detailing the making of bidding dossiers for construction and installation.

c) The Minister of Planning and Investment's Circular No. 05/2015/TT-BKHDT dated June 16, 2015, detailing the making of bidding dossiers for procurement of goods.

d) The Minister of Planning and Investment's Circular No. 14/2016/TT-BKHDT dated September 29, 2016, detailing the making of bidding dossiers for non-consulting services.

dd) The Minister of Planning and Investment’s Circular No. 04/2017/TT-BKHDT dated November 15, 2017, on prescribing in detail the contractor selection via the National E-Public Procurement system.

e) The Minister of Planning and Investment's Circular No. 05/2018/TT-BKHDT dated December 10, 2018, providing detailed regulations on making of e-bid dossier evaluation reports for bidding packages for which contractors are selected in the e-public procurement system.

g) The Minister of Planning and Investment's Circular No. 11/2019/TT-BKHDT dated December 16, 2019, on stipulating in detail the provision and posting of information on bidding, roadmap for organization of online selection of contractors, and management and use of unreturned bid security and contract performance security amounts.

h) The Minister of Planning and Investment's Circular No. 05/2020/TT-BKHDT dated June 30, 2020, on amending and supplementing a number of articles of Circular No. 04/2017/TT-BKHDT dated November 15, 2017 of the Ministry of Planning and Investment on prescribing in detail the contractor selection via the National E-Public Procurement system.

i) Articles 7, 8, 9, 10 and 13 of the Minister of Planning and Investment's Circular No. 06/2020/TT-BKHDT dated September 18, 2020, guiding the implementation of the Government’s Decree No. 25/2020/ND-CP of February 28, 2020, detailing a number of articles of the Bidding Law regarding investor selection.

k) Clause 4, Article 8 of the Minister of Planning and Investment's Circular No. 09/2021/TT-BKHDT dated November 16, 2021, guiding the selection of investors to implement investment projects in the form of public-private partnership and land-using investment projects.

2. For bidding packages for procurement of goods divided into several parts:

a) For the bidding package for which the bidding dossier has been issued before January 01, 2023, the selection of contractors shall be carried out according to the issued bidding dossier and the provisions of law in effect at that time;

b) From January 01, 2023, if the approved bidding package does not apply the online contractor selection and has not yet issued the bidding dossier, the contractor selection shall be organized online on the basis of ensuring of the roadmap specified in Article 37 of Circular No. 08/2022/TT-BKHDT. In such cases, competent persons may not change the contractor selection plan.

Article 3. Effect

This Circular takes effect from August 01, 2022./.

 

The Minister

NGUYEN CHI DUNG

Please log in to a subscriber account to see the full text. Don’t have an account? Register here
Please log in to a subscriber account to see the full text. Don’t have an account? Register here
Processing, please wait...
LuatVietnam.vn is the SOLE distributor of English translations of Official Gazette published by the Vietnam News Agency

VIETNAMESE DOCUMENTS

Circular 16/2022/TT-BKHĐT DOC (Word)

This utility is available to subscribers only. Please log in to a subscriber account to download. Don’t have an account? Register here

Circular 16/2022/TT-BKHĐT PDF (Original)

This utility is available to subscribers only. Please log in to a subscriber account to download. Don’t have an account? Register here

ENGLISH DOCUMENTS

LuatVietnam's translation
Circular 16/2022/TT-BKHĐT DOC (Word)

This utility is available to subscribers only. Please log in to a subscriber account to download. Don’t have an account? Register here

Circular 16/2022/TT-BKHĐT PDF

This utility is available to subscribers only. Please log in to a subscriber account to download. Don’t have an account? Register here

* Note: To view documents downloaded from LuatVietnam.vn, please install DOC, DOCX and PDF file readers
For further support, please call 19006192

SAME CATEGORY

Circular No. 12/2022/TT-BKHDT dated June 30, 2022 of the Ministry of Planning and Investment providing in detail the making of bidding dossiers for bidding packages on procurement regulated by the Comprehensive and Progressive Agreement for Trans-Pacific Partnership, the Free Trade Agreement between the Socialist Republic of Vietnam and the European Union and the Free Trade Agreement between the Socialist Republic of Vietnam and the United Kingdom of Great Britain and Northern Ireland

Circular No. 12/2022/TT-BKHDT dated June 30, 2022 of the Ministry of Planning and Investment providing in detail the making of bidding dossiers for bidding packages on procurement regulated by the Comprehensive and Progressive Agreement for Trans-Pacific Partnership, the Free Trade Agreement between the Socialist Republic of Vietnam and the European Union and the Free Trade Agreement between the Socialist Republic of Vietnam and the United Kingdom of Great Britain and Northern Ireland

Bidding - Competition , Investment

Circular No. 15/2022/TT-BKHDT dated June 30, 2022 of the Ministry of Planning and Investment providing in detail the making of bidding dossiers for bidding packages on construction and installation regulated by the Comprehensive and Progressive Agreement for Trans-Pacific Partnership, the Free Trade Agreement between the Socialist Republic of Vietnam and the European Union and the Free Trade Agreement between the Socialist Republic of Vietnam and the United Kingdom of Great Britain and Northern Ireland

Circular No. 15/2022/TT-BKHDT dated June 30, 2022 of the Ministry of Planning and Investment providing in detail the making of bidding dossiers for bidding packages on construction and installation regulated by the Comprehensive and Progressive Agreement for Trans-Pacific Partnership, the Free Trade Agreement between the Socialist Republic of Vietnam and the European Union and the Free Trade Agreement between the Socialist Republic of Vietnam and the United Kingdom of Great Britain and Northern Ireland

Bidding - Competition , Investment

loading